Courtesy illustration Child Development Center
By Kevin Wilson: Cannon Connections
Editor’s Note: The following list covers the next three years
of projects at the base, totaling $154.4 million. Total construction
costs are estimated at $536 million through 2015.
Fiscal year 2008
• Project: Airmen’s Center
Estimated completion: June
Estimated cost: $10 million
Purpose: Center includes a new dining facility, recreation center and a post office.
• Project: Fuels storage area
Estimated completion: February
Estimated cost: $12.3 million
Purpose: Repairs to fuel storage tanks, upgrades to fuel loading area.